Execution Management 02: Three ways time gets wasted during project execution 

By Sanjeev Gupta, founder & CEO, Realization Technologies -- Manufacturing Business Technology, 9/12/2008 1:25:00 PM

In the last Execution Management Minute, we established that managers must focus on time efficiency rather than resource efficiency in projects. A natural question is, “How can we squeeze projects for time when it is difficult to meet even current timelines in projects?” 
After all, projects are riddled with uncertainties. Work usually takes longer than estimated; technical issues materialize; vendors don’t deliver on time; approvals get held up; resources are not available as promised. No matter how painstakingly you plan, in execution you will have surprises!
But a closer look reveals that rather than uncertainties themselves being the main culprit behind project delays and overruns, the major problem is in how we manage these uncertainties.
Management mistake No. 1: Starting projects ASAP.
Since project managers recognize that not getting resources in a timely manner is a major problem, they compete aggressively for shared resources. They start a project as soon as possible, hoping that it will maximize their chances of securing the needed resources. In reality, the consequence is the exact opposite. Resources become thinly spread, queues increase, and projects take much longer than they should.
Management mistake No. 2: Treating planning estimates as execution commitments.
This flawed practice means estimates must include safety time to account for the high uncertainty in projects. Project plans get longer yet managers are willing to pay this price to ensure that projects will finish on time. Unfortunately, in execution, while most tasks finish on time, almost none of the tasks finish early. This phenomenon of work expanding to fill the time available is called Parkinson’s Law. To compound, some tasks still take longer than planned, causing the entire project to be still late! Bottom line: Local commitments only prolong the project plan without significantly increasing on-time delivery.
Management mistake No. 3: Lacking good task-level priorities in execution.
Not knowing which tasks to work on when, resources get pulled in divergent directions. Project managers add to the confusion by pressuring the resources to start working on their project’s tasks without worrying about the impact on other’s project tasks. Rather than helping all projects make progress, assigning resources in this way actually causes all projects to become stalled.

Our experience with more than 200 project-based organizations is that 20 percent to 50 percent of the time and capacity involving projects is wasted due to traditional management practices.
But this can change. Managers no longer need to feel stymied by traditional practices. The Critical Chain method provides new, effective rules of managing project execution. And that will be the topic of our next Execution Management Minute.
As a recipient of the Franz Edelman award and Chief of Staff Team Excellence award for its work with Warner Robins Air Logistics Center, Realization has helped more than 200 organizations throughout the world increase speed and efficiency in new product development; engineer-to-order manufacturing; construction; maintenance, repair and overhaul; and other project-based operations.  Learn more now.

Email
Print
Reprints/License
RSS
Talkback
Reed Business Information Resource Center

Featured Company


Related Resources

Advertisement

Related Microsite Content

Related Links

More Content
  • Blogs
  • Webcasts
  • Podcasts

Jim Brown

PLM and Profitability

Jim Brown, President and founder of Tech-Clarity
November 12, 2009
Research Rap: Role of Component and Compliance Information in Supply Risk Management
A quick peek into some research on … the importance of good supply chain...
More

Roberto Michel

Operation Green

Roberto Michel, Senior Contributing Editor, Manufacturing Business Technology
November 11, 2009
Plant-focused software vendors correlating energy with production management
The last few days have seen more announcements from plant automation software...
More

VIEW ALL BLOGS RSS
  • Enterprise PLM


    Is your company ready for Enterprise PLM?

    Enterprise product life-cycle management (PLM) encompasses nine business processes—among them the much-embraced Design for Supply and Cost. This podcast sets up the relationship between PLM software and Enterprise PLM processes in basic terms, including the bonuses found in time-to-market and product quality.

    Sarvesh Jagannivas
    Speaker: Sarvesh Jagannivas
    Vice President of Marketing for Oracle’s Agile PLM software group
    Sidney Hill
    Moderator: Sidney Hill
    Executive Editor of Manufacturing Business Technology
    Hear It Now

Advertisement
ARCbanner
NEWSLETTERS
Mid-Day Report
Innovation Strategies
Intelligent Manufacturing
Lean Enterprise



Please read our Privacy Policy

About Us   |   Advertising Info   |   Site Map   |   Contact Us   |   FREE Subscription   |   Affiliate Links   |   RSS
© 2009 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites